Task

Grohe AG, site of Porta Westfalica, commissioned REFA Consulting AG to neutrally measure and evaluate the assembly times of installation systems for dry-wall lining from the perspective of an expert.

The "Grohe Rapid SL" installation system was compared with comparable systems from five competitors based on the installation of a WC element.

The assembly times were determined according to the principles of the REFA methodology which can be applied in all branches of trade, industry, production and administration. The assembly times were recorded by a REFA technician with many years of professional experience.

Case Study Montagezeiten

To ensure the objectivity and neutrality of the results, the work was carried out in the company’s prototype workshop in Porta Westfalica by qualified technicians from an external installation company (not by employees of Grohe AG).

The times for the operations/time modules concerned were measured and evaluated and the data was then collected in a calculation sheet.

The technicians each worked in rotation under otherwise identical conditions. After statistical evaluation, the data obtained is sufficiently accurate for calculation purposes.

Procedure

Nine assembly operations were carried out on the product, in detail:

  • Instructing the technicians
  • Carrying out trial assemblies
  • Measuring the times of 9 assembly operations
  • Change of technicians after each assembly cycle.

The Grohe AG website contains further information on the practical test.

Results

Fallstudie Montage

Case Study Montage

Results of the time study in detail

Case Study Montagezeiten

Your contact

Bettina DirksBettina Dirks
Coordination Consulting
phone +49(0)89 42 01 74 71
This email address is being protected from spambots. You need JavaScript enabled to view it.

Contact Office Switzerland
EN - FR - IT - ES
phone +41(0)44 500 2328
This email address is being protected from spambots. You need JavaScript enabled to view it.